February Sewage Works Update

Thames Water report that their improvements works at Chesham Sewage Treatment Works are proceeding extremely well and are on schedule for completion by the end of March 2018. 

The update on works so far is:
- the new aeration technology is working effectively
- they are continuing to test/monitor the newly installed equipment which is currently operating how they would expect it to
- they have almost completed the concrete paths and repairs to road drainage on site
- the new scraper bridge has now been lifted into place
- they are continuing to work on improvements to reduce the noise from the aeration piepwork at site

The working hours are Monday to Friday, 7.30am to 5pm.

They are not expecting an increase in odour while the work is carried out, but there may be an increase in noise and vehicle movements; Thames Water will do their best to keep disruption to a minimum. 

If you have any queries or concerns, you can get in touch with Thames Water on 0800 316 9800, selecting Option 2 and quoting reference number BB970397. 